Dailymaverick logo

Op-eds

Op-eds

Risks identified in Eskom’s 2026-30 system adequacy outlook require a critical balancing act

Eskom's latest report reveals that while South Africa's power supply might look good on paper, the reality is a precarious dance between regional shortages and grid congestion, with the looming retirement of coal plants threatening to plunge us back into the dark ages – unless, of course, our gas turbines arrive on time to save the day.
Risks identified in Eskom’s 2026-30 system adequacy outlook require a critical balancing act (Photo: Unsplash / Andrey Metelev)

Eskom’s Medium-Term System Adequacy Outlook (MTSAO) 2026-2030 Report provides a detailed, probabilistic assessment of whether South Africa’s generation fleet and network will be able to meet demand during the next five years.

Published on 30 October 2025 in line with the South African Grid Code, it is not a planning document but an adequacy review, measuring whether available and expected resources can keep the lights on under varying assumptions.

The 2025 edition represents a methodological change: it replaces the traditional single-node model with a new multinodal analysis that maps generation and demand to specific transmission nodes. This approach exposes the regional dimension of adequacy – revealing where local shortfalls or grid congestion could cause load shedding even when national generation appears sufficient.

Demand scenarios

The study models three demand trajectories linked to GDP growth of 1.7%, 2.7%, and 3.5%. Under the moderate scenario – adopted for the base case – electricity demand rises from 243 terawatt-hours (TWh) in 2024 to 264TWh in 2030, an annual growth of 1.4%. 

These projections depend heavily on industrial performance and on the continuation of the Hydro Cahora Bassa import agreement, which supplies 1.15GW until at least March 2030. The System Operator cautions that early termination would materially change the results. Meanwhile, small-scale embedded generation has already reached an estimated 6.9GW, but growth has slowed as the frequency of load shedding declined in 2025.

Supply dynamics

Total installed capacity is about 65GW – dominated by coal, followed by solar PV, wind, diesel, hydro, pumped storage, nuclear, battery energy storage (BES) and other minor technologies. Yet the outlook identifies a looming base-supply cliff: 8.4GW of Eskom coal capacity is scheduled for retirement in 2029 to 2030, and the 1.15GW Cahora Bassa import from Mozambique expires simultaneously, creating a 9.5GW potential loss of firm supply. 

While Eskom’s review of its coal-fired power shutdown schedule has postponed closures to 2029, the decline remains inevitable. Koeberg’s life extension to 2044 partly offsets this, but the fleet’s energy availability factor (EAF) remains critical. Under the moderate-case average of 60% EAF, adequacy is maintained; a fall to 55% EAF reintroduces risks of load shedding. 

Publicly procured renewables have expanded rapidly – from 0.47GW in 2013 to 7.32GW in 2025 – and will reach ≈ 11GW through REIPPPP Bid Windows 5 to 7 and RMIPPPP. Private projects (behind-the-meter and wheeling) will add another 11.5GW (≈ 7GW solar, ≈ 4.4GW wind), while Eskom’s own hybrid and BES projects contribute 1.89GW and IPP BES projects add ≈ 0.5GW, by 2028. 

Created using Gemini

The most uncertain component is the planned 6GW of combined-cycle gas turbines (CCGTs) – half Eskom, half IPPs – assumed to enter service in 2030. Any delay would raise unserved energy beyond 4TWh and push diesel-driven open-cycle gas turbine (OCGT) utilisation above 40%.

Adequacy metrics and methodology

Adequacy is deemed acceptable when annual unserved energy is below 20 gigawatt-hours and OCGT capacity factors remain under 6%. The modelling uses Monte Carlo hourly simulations combining randomised demand, renewable output and outage events.

Four scenarios are analysed: 

  • Base case (committed capacity, including CCGTs);
  • All new capacity (every project expected by 2030);
  • Risk-adjusted capacity (excludes delayed gas); and
  • Accelerated build (adds 4.7GW of fast-tracked private projects).

This framework allows comparison of outcomes depending on how quickly new generation is realised and how well retirements and additions are synchronised.

Results

The system remains broadly adequate until 2029 under the moderate EAF and demand assumptions. Unserved energy spikes in 2029 as 5.26GW of coal capacity closes, then declines in 2030 once 6GW of CCGTs are assumed to come online. If gas slips beyond 2030, the supply gap deepens dramatically. 

OCGT use stays minimal through 2028 but surges when coal units retire, reaching unsustainable levels if CCGTs are delayed. The analysis reinforces the need to align gas commissioning with coal shutdowns. 

Excess energy, mainly from solar PV, becomes increasingly prevalent. In the accelerated-build scenario, more than 5TWh of curtailment occurs by 2028. Transmission constraints, rather than true oversupply, cause most of it, with the Poseidon MTS (main transmission substation) in the Eastern Cape showing curtailments above 70% until grid reinforcements arrive. 

The study highlights simultaneous daily surpluses and shortages – excess solar during midday followed by evening deficits – signalling the onset of South Africa’s characteristic “duck-curve” effect unless significant BES capacity is added.

Transmission adequacy

The new multinodal model reveals that adequacy is now as much about where power is generated as how much exists nationally. Generation shortages remain the main cause of unserved energy, but transmission bottlenecks are increasingly material. Key load centres such as in Gauteng and North West face localised deficits owing to network congestion.  

Major transmission upgrades – new 400kV MTS substations at Kyalami and Bighorn, among others – are planned but are largely only operational beyond 2030. In the interim, the System Operator must rely on operational measures such as sectionalising and contingency limits to manage congestion.

The findings strengthen the case for accelerated investment through the new National Transmission Company South Africa (NTCSA) and National Treasury’s Transmission Financing Facility.

Operational and policy implications

The MTSAO makes it clear that system reliability depends on flexibility, not only capacity. Without significant increases in BES capacity, daily ramping of coal units up to 7GW to accommodate solar generation imposes wear and could reverse recent EAF gains, which improved from 55% in FY 2023 to ≈ 63 % in FY 2025.  

Gas generation is identified as a bridge technology, yet infrastructure delays and regulatory uncertainty threaten timely delivery. Without gas, 2030 could see more than 4TWh of unmet demand – equivalent to roughly 80 days of Stage 4 load shedding.  

However, private renewable energy generation expansion is reshaping the market, with more than 11GW of projects at an advanced stage, highlighting investor appetite. However, uncoordinated roll-out ahead of grid expansion risks worsening curtailment, especially in coastal provinces.

Finally, frequency-stability data show rising volatility linked to solar peaks, underlining the need for fast-response BES and demand-side resources to participate in ancillary-service markets.

Policy links

Although non-prescriptive, the MTSAO’s outcomes align closely with national policy instruments. Its adequacy data underpin the Integrated Resource Plan, IRP 2025, reinforce priorities in Eskom’s Transmission Development Plan 2025-2035, and provide empirical grounding for the Electricity Regulation Amendment Act (2025), which will enable the competitive wholesale electricity market. 

Together, these frameworks point to a future system built on diversified, flexible and regionally balanced supply.

Key risks

Three structural risks dominate the outlook: 

  • Coal-retirement gap: 9.5GW of firm capacity shut down by 2030 without guaranteed replacement;
  • Gas-to-power delay: Slippage beyond 2030 raises unserved energy above 4TWh and OCGT use above 45%; and
  • Transmission congestion: Severe curtailment in the Eastern Cape and other regions until new substations are operational.

Additional threats include possible closure of coal stations after 2030 if environmental exemptions lapse, accelerated equipment degradation from cycling, and rising frequency instability as inverter-based generation grows, unless synchronous condensers and/or synthetic inertia from grid-forming BES is added.

Outlook

Eskom’s Medium-Term System Adequacy Outlook 2026-2030 portrays a power system entering a delicate transition. Adequacy risks now exist on both sides of the equation: shortfalls from delayed firm capacity and surpluses from rapid renewable growth. Managing this dual challenge demands careful synchronisation of generation, gas infrastructure and grid expansion.  

Sustaining 60% EAF, commissioning 6GW of CCGTs on time, and executing transmission reinforcements before 2030 are essential conditions for stability. 

The study ultimately reframes South Africa’s energy question from “How many megawatts?” to “How flexible and well-timed are they?” – a shift that will define whether the country can move from chronic shortage to sustainable adequacy by the end of the decade. DM

Chris Yelland is managing director of EE Business Intelligence.

© Copyright 2025 – EE Business Intelligence (Pty) Ltd. All rights reserved. This article may not be published without the written permission of EE Business Intelligence.

All Article Properties:

{
  "objectType": "Article",
  "id": "2958736",
  "signature": "Article:2958736",
  "url": "https://prod.dailymaverick.co.za/article/2025-11-03-risks-flagged-in-eskoms-2026-30-system-adequacy-outlook-require-critical-balancing-act/",
  "shorturl": "https://www.dailymaverick.co.za/article/2958736",
  "slug": "risks-flagged-in-eskoms-2026-30-system-adequacy-outlook-require-critical-balancing-act",
  "contentType": {
    "id": "1",
    "name": "Article",
    "slug": "article",
    "editor": "default"
  },
  "views": 0,
  "comments": 0,
  "preview_limit": null,
  "rating": 0,
  "excludedFromGoogleSearchEngine": 0,
  "status": "publish",
  "title": "Risks identified in Eskom’s 2026-30 system adequacy outlook require a critical balancing act",
  "firstPublished": "2025-11-03 19:15:51",
  "lastUpdate": "2025-11-03 23:39:33",
  "categories": [
    {
      "id": "405817",
      "name": "Op-eds",
      "signature": "Category:405817",
      "slug": "op-eds",
      "typeId": {
        "typeId": "1",
        "name": "Daily Maverick",
        "slug": "",
        "includeInIssue": "0",
        "shortened_domain": "",
        "stylesheetClass": "",
        "domain": "prod.dailymaverick.co.za",
        "articleUrlPrefix": "",
        "access_groups": "[]",
        "locale": "",
        "preview_limit": null
      },
      "parentId": null,
      "parent": [],
      "image": "",
      "cover": "",
      "logo": "",
      "paid": "0",
      "objectType": "Category",
      "url": "https://prod.dailymaverick.co.za/category/op-eds/",
      "cssCode": "",
      "template": "default",
      "tagline": "",
      "link_param": null,
      "description": "",
      "metaDescription": "",
      "order": "0",
      "pageId": null,
      "articlesCount": null,
      "allowComments": "1",
      "accessType": "freecount",
      "status": "1",
      "children": [],
      "cached": false
    }
  ],
  "access_groups": [],
  "access_control": false,
  "counted_in_paywall": true,
  "content_length": 8902,
  "contents": "<p><span style=\"font-weight: 400;\">Eskom’s </span><a href=\"https://www.ntcsa.co.za/wp-content/uploads/2025/10/Medium-Term-System-Adequacy-Outlook-2026-2030.pdf\"><span style=\"font-weight: 400;\">Medium-Term System Adequacy Outlook (MTSAO) 2026-2030 Report</span></a><span style=\"font-weight: 400;\"> provides a detailed, probabilistic assessment of whether South Africa’s generation fleet and network will be able to meet demand during the next five years.</span></p><p><span style=\"font-weight: 400;\">Published on 30 October 2025 in line with the South African Grid Code, it is not a planning document but an adequacy review, measuring whether available and expected resources can keep the lights on under varying assumptions.</span></p><p><span style=\"font-weight: 400;\">The 2025 edition represents a methodological change: it replaces the traditional single-node model with a new multinodal analysis that maps generation and demand to specific transmission nodes. This approach exposes the regional dimension of adequacy – revealing where local shortfalls or grid congestion could cause load shedding even when national generation appears sufficient.</span></p><h4><b>Demand scenarios</b></h4><p><span style=\"font-weight: 400;\">The study models three demand trajectories linked to GDP growth of 1.7%, 2.7%, and 3.5%. Under the moderate scenario – adopted for the base case – electricity demand rises from 243 terawatt-hours (TWh) in 2024 to 264TWh in 2030, an annual growth of 1.4%. </span></p><p><span style=\"font-weight: 400;\">These projections depend heavily on industrial performance and on the continuation of the Hydro Cahora Bassa import agreement, which supplies 1.15GW until at least March 2030. The System Operator cautions that early termination would materially change the results. Meanwhile, small-scale embedded generation has already reached an estimated 6.9GW, but growth has slowed as the frequency of load shedding declined in 2025.</span></p><h4><b>Supply dynamics</b></h4><p><span style=\"font-weight: 400;\">Total installed capacity is about 65GW – dominated by coal, followed by solar PV, wind, diesel, hydro, pumped storage, nuclear, battery energy storage (BES) and other minor technologies. Yet the outlook identifies a looming base-supply cliff: 8.4GW of Eskom coal capacity is scheduled for retirement in 2029 to 2030, and the 1.15GW Cahora Bassa import from Mozambique expires simultaneously, creating a 9.5GW potential loss of firm supply. </span></p><p><span style=\"font-weight: 400;\">While Eskom’s review of its coal-fired power shutdown schedule has postponed closures to 2029, the decline remains inevitable. Koeberg’s life extension to 2044 partly offsets this, but the fleet’s energy availability factor (EAF) remains critical. Under the moderate-case average of 60% EAF, adequacy is maintained; a fall to 55% EAF reintroduces risks of load shedding. </span></p><p><span style=\"font-weight: 400;\">Publicly procured renewables have expanded rapidly – from 0.47GW in 2013 to 7.32GW in 2025 – and will reach ≈ 11GW through REIPPPP Bid Windows 5 to 7 and RMIPPPP. Private projects (behind-the-meter and wheeling) will add another 11.5GW (≈ 7GW solar, ≈ 4.4GW wind), while Eskom’s own hybrid and BES projects contribute 1.89GW and IPP BES projects add ≈ 0.5GW, by 2028. </span></p><figure style='float: none; margin: 5px; '><img loading=\"lazy\" src='https://cdn.dailymaverick.co.za/i/6JBkaiU0bVO_tHg-TxHnKxz-Ieg=/200x100/smart/filters:strip_exif()/file/dailymaverick/wp-content/uploads/2025/11/Code_Generated_Image.png' alt='' title=' Created using Gemini' srcset='https://cdn.dailymaverick.co.za/i/6JBkaiU0bVO_tHg-TxHnKxz-Ieg=/200x100/smart/filters:strip_exif()/file/dailymaverick/wp-content/uploads/2025/11/Code_Generated_Image.png 200w, https://cdn.dailymaverick.co.za/i/nXWXFS4FA8IlSDk14No1Noz70dc=/450x0/smart/file/dailymaverick/wp-content/uploads/2025/11/Code_Generated_Image.png 450w, https://cdn.dailymaverick.co.za/i/KG-5RVZq-X7Focf9gEe9Ny7QRnA=/800x0/smart/filters:strip_exif()/file/dailymaverick/wp-content/uploads/2025/11/Code_Generated_Image.png 800w, https://cdn.dailymaverick.co.za/i/SJsJT7v4OWQIGJj7_BFC8-4_gaA=/1200x0/smart/filters:strip_exif()/file/dailymaverick/wp-content/uploads/2025/11/Code_Generated_Image.png 1200w, https://cdn.dailymaverick.co.za/i/H9Gh1fXmmaOH2fUy8ypDtNCJZR0=/1600x0/smart/filters:strip_exif()/file/dailymaverick/wp-content/uploads/2025/11/Code_Generated_Image.png 1600w' style='object-position: 50% 50%'><figcaption> Created using Gemini </figcaption></figure><p><span style=\"font-weight: 400;\">The most uncertain component is the planned 6GW of combined-cycle gas turbines (CCGTs) – half Eskom, half IPPs – assumed to enter service in 2030. Any delay would raise unserved energy beyond 4TWh and push diesel-driven open-cycle gas turbine (OCGT) utilisation above 40%.</span></p><h4><b>Adequacy metrics and methodology</b></h4><p><span style=\"font-weight: 400;\">Adequacy is deemed acceptable when annual unserved energy is below 20 gigawatt-hours and OCGT capacity factors remain under 6%. The modelling uses Monte Carlo hourly simulations combining randomised demand, renewable output and outage events.</span></p><p><span style=\"font-weight: 400;\">Four scenarios are analysed: </span></p><ul><li>Base case (committed capacity, including CCGTs);</li><li>All new capacity (every project expected by 2030);</li><li>Risk-adjusted capacity (excludes delayed gas); and</li><li>Accelerated build (adds 4.7GW of fast-tracked private projects).</li></ul><p><span style=\"font-weight: 400;\">This framework allows comparison of outcomes depending on how quickly new generation is realised and how well retirements and additions are synchronised.</span></p><h4><b>Results</b></h4><p><span style=\"font-weight: 400;\">The system remains broadly adequate until 2029 under the moderate EAF and demand assumptions. Unserved energy spikes in 2029 as 5.26GW of coal capacity closes, then declines in 2030 once 6GW of CCGTs are assumed to come online. If gas slips beyond 2030, the supply gap deepens dramatically. </span></p><p><span style=\"font-weight: 400;\">OCGT use stays minimal through 2028 but surges when coal units retire, reaching unsustainable levels if CCGTs are delayed. The analysis reinforces the need to align gas commissioning with coal shutdowns. </span></p><p><span style=\"font-weight: 400;\">Excess energy, mainly from solar PV, becomes increasingly prevalent. In the accelerated-build scenario, more than 5TWh of curtailment occurs by 2028. Transmission constraints, rather than true oversupply, cause most of it, with the Poseidon MTS (main transmission substation) in the Eastern Cape showing curtailments above 70% until grid reinforcements arrive. </span></p><p><span style=\"font-weight: 400;\">The study highlights simultaneous daily surpluses and shortages – excess solar during midday followed by evening deficits – signalling the onset of South Africa’s characteristic “duck-curve” effect unless significant BES capacity is added.</span></p><h4><b>Transmission adequacy</b></h4><p><span style=\"font-weight: 400;\">The new multinodal model reveals that adequacy is now as much about where power is generated as how much exists nationally. Generation shortages remain the main cause of unserved energy, but transmission bottlenecks are increasingly material. Key load centres such as in Gauteng and North West face localised deficits owing to network congestion.  </span></p><p><span style=\"font-weight: 400;\">Major transmission upgrades – new 400kV MTS substations at Kyalami and Bighorn, among others – are planned but are largely only operational beyond 2030. In the interim, the System Operator must rely on operational measures such as sectionalising and contingency limits to manage congestion.</span></p><p><span style=\"font-weight: 400;\">The findings strengthen the case for accelerated investment through the new National Transmission Company South Africa (NTCSA) and National Treasury’s Transmission Financing Facility.</span></p><h4><b>Operational and policy implications</b></h4><p><span style=\"font-weight: 400;\">The MTSAO makes it clear that system reliability depends on flexibility, not only capacity. Without significant increases in BES capacity, daily ramping of coal units up to 7GW to accommodate solar generation imposes wear and could reverse recent EAF gains, which improved from 55% in FY 2023 to ≈ 63 % in FY 2025.  </span></p><p><span style=\"font-weight: 400;\">Gas generation is identified as a bridge technology, yet infrastructure delays and regulatory uncertainty threaten timely delivery. Without gas, 2030 could see more than 4TWh of unmet demand – equivalent to roughly 80 days of Stage 4 load shedding.  </span></p><p><span style=\"font-weight: 400;\">However, private renewable energy generation expansion is reshaping the market, with more than 11GW of projects at an advanced stage, highlighting investor appetite. However, uncoordinated roll-out ahead of grid expansion risks worsening curtailment, especially in coastal provinces.</span></p><p><span style=\"font-weight: 400;\">Finally, frequency-stability data show rising volatility linked to solar peaks, underlining the need for fast-response BES and demand-side resources to participate in ancillary-service markets.</span></p><h4><b>Policy links</b></h4><p><span style=\"font-weight: 400;\">Although non-prescriptive, the MTSAO’s outcomes align closely with national policy instruments. Its adequacy data underpin the Integrated Resource Plan, IRP 2025, reinforce priorities in Eskom’s Transmission Development Plan 2025-2035, and provide empirical grounding for the Electricity Regulation Amendment Act (2025), which will enable the competitive wholesale electricity market. </span></p><p><span style=\"font-weight: 400;\">Together, these frameworks point to a future system built on diversified, flexible and regionally balanced supply.</span></p><h4><b>Key risks</b></h4><p><span style=\"font-weight: 400;\">Three structural risks dominate the outlook: </span></p><ul><li>Coal-retirement gap: 9.5GW of firm capacity shut down by 2030 without guaranteed replacement;</li><li>Gas-to-power delay: Slippage beyond 2030 raises unserved energy above 4TWh and OCGT use above 45%; and</li><li>Transmission congestion: Severe curtailment in the Eastern Cape and other regions until new substations are operational.</li></ul><p><span style=\"font-weight: 400;\">Additional threats include possible closure of coal stations after 2030 if environmental exemptions lapse, accelerated equipment degradation from cycling, and rising frequency instability as inverter-based generation grows, unless synchronous condensers and/or synthetic inertia from grid-forming BES is added.</span></p><h4><b>Outlook</b></h4><p><span style=\"font-weight: 400;\">Eskom’s Medium-Term System Adequacy Outlook 2026-2030 portrays a power system entering a delicate transition. Adequacy risks now exist on both sides of the equation: shortfalls from delayed firm capacity and surpluses from rapid renewable growth. Managing this dual challenge demands careful synchronisation of generation, gas infrastructure and grid expansion.  </span></p><p><span style=\"font-weight: 400;\">Sustaining 60% EAF, commissioning 6GW of CCGTs on time, and executing transmission reinforcements before 2030 are essential conditions for stability. </span></p><p><span style=\"font-weight: 400;\">The study ultimately reframes South Africa’s energy question from “How many megawatts?” to “How flexible and well-timed are they?” – a shift that will define whether the country can move from chronic shortage to sustainable adequacy by the end of the decade. </span><b>DM</b></p><p><i><span style=\"font-weight: 400;\">Chris Yelland is managing director of EE Business Intelligence.</span></i></p><p><i><span style=\"font-weight: 400;\">© Copyright 2025 – EE Business Intelligence (Pty) Ltd. All rights reserved. This article may not be published without the written permission of EE Business Intelligence.</span></i></p>",
  "teaser": "Risks flagged in Eskom’s 2026-30 system adequacy outlook require critical balancing act",
  "externalUrl": "",
  "sponsor": null,
  "authors": [
    {
      "id": "141",
      "name": "Chris Yelland",
      "image": "https://cdn.dailymaverick.co.za/dailymaverick/wp-content/uploads/chris-yelland-column-photo.jpg",
      "url": "https://www.dailymaverick.co.za/author/chrisyelland/",
      "editorialName": "chrisyelland",
      "department": "",
      "name_latin": ""
    }
  ],
  "description": "The Eskom report portrays a power system entering a delicate transition. Adequacy risks now exist on both sides of the equation: shortfalls from delayed firm capacity and surpluses from rapid renewable growth. Managing this dual challenge demands careful synchronisation of generation, gas infrastruc",
  "keywords": [
    {
      "type": "Keyword",
      "data": {
        "keywordId": "2741",
        "name": "Eskom",
        "url": "https://www.dailymaverick.co.za/article_tag//",
        "slug": "eskom",
        "description": "Eskom is the primary electricity supplier and generator of power in South Africa. It is a state-owned enterprise that was established in 1923 as the Electricity Supply Commission (ESCOM) and later changed its name to Eskom. The company is responsible for generating, transmitting, and distributing electricity to the entire country, and it is one of the largest electricity utilities in the world, supplying about 90% of the country's electricity needs. It generates roughly 30% of the electricity used\r\nin Africa.\r\n\r\nEskom operates a variety of power stations, including coal-fired, nuclear, hydro, and renewable energy sources, and has a total installed capacity of approximately 46,000 megawatts. The company is also responsible for maintaining the electricity grid infrastructure, which includes power lines and substations that distribute electricity to consumers.\r\n\r\nEskom plays a critical role in the South African economy, providing electricity to households, businesses, and industries, and supporting economic growth and development. However, the company has faced several challenges in recent years, including financial difficulties, aging infrastructure, and operational inefficiencies, which have led to power outages and load shedding in the country.\r\n\r\nDaily Maverick has reported on this extensively, including its recently published investigations from the Eskom Intelligence Files which demonstrated extensive sabotage at the power utility. Intelligence reports obtained by Daily Maverick linked two unnamed senior members of President Cyril Ramaphosa’s Cabinet to four criminal cartels operating inside Eskom. The intelligence links the cartels to the sabotage of Eskom’s power stations and to a programme of political destabilisation which has contributed to the current power crisis.",
        "articlesCount": 0,
        "replacedWith": null,
        "display_name": "Eskom",
        "translations": null,
        "collection_id": null,
        "image": ""
      }
    },
    {
      "type": "Keyword",
      "data": {
        "keywordId": "5980",
        "name": "Energy",
        "url": "https://www.dailymaverick.co.za/article_tag//",
        "slug": "energy",
        "description": "",
        "articlesCount": 0,
        "replacedWith": null,
        "display_name": "Energy",
        "translations": null,
        "collection_id": null,
        "image": ""
      }
    },
    {
      "type": "Keyword",
      "data": {
        "keywordId": "18736",
        "name": "Chris Yelland",
        "url": "https://www.dailymaverick.co.za/article_tag//",
        "slug": "chris-yelland",
        "description": "",
        "articlesCount": 0,
        "replacedWith": null,
        "display_name": "Chris Yelland",
        "translations": null,
        "collection_id": null,
        "image": ""
      }
    },
    {
      "type": "Keyword",
      "data": {
        "keywordId": "47787",
        "name": "gas",
        "url": "https://www.dailymaverick.co.za/article_tag//",
        "slug": "gas",
        "description": "",
        "articlesCount": 0,
        "replacedWith": null,
        "display_name": "gas",
        "translations": null,
        "collection_id": null,
        "image": ""
      }
    },
    {
      "type": "Keyword",
      "data": {
        "keywordId": "132321",
        "name": "Load Shedding",
        "url": "https://www.dailymaverick.co.za/article_tag//",
        "slug": "load-shedding",
        "description": "",
        "articlesCount": 0,
        "replacedWith": null,
        "display_name": "Load Shedding",
        "translations": null,
        "collection_id": null,
        "image": ""
      }
    },
    {
      "type": "Keyword",
      "data": {
        "keywordId": "357353",
        "name": "power generation",
        "url": "https://www.dailymaverick.co.za/article_tag//",
        "slug": "power-generation",
        "description": "",
        "articlesCount": 0,
        "replacedWith": null,
        "display_name": "power generation",
        "translations": null,
        "collection_id": null,
        "image": ""
      }
    },
    {
      "type": "Keyword",
      "data": {
        "keywordId": "407743",
        "name": "grid expansion",
        "url": "https://www.dailymaverick.co.za/article_tag//",
        "slug": "grid-expansion",
        "description": "",
        "articlesCount": 0,
        "replacedWith": null,
        "display_name": "grid expansion",
        "translations": null,
        "collection_id": null,
        "image": ""
      }
    },
    {
      "type": "Keyword",
      "data": {
        "keywordId": "440419",
        "name": "Medium-Term System Adequacy Outlook 2026-2030",
        "url": "https://www.dailymaverick.co.za/article_tag//",
        "slug": "mediumterm-system-adequacy-outlook-20262030",
        "description": "",
        "articlesCount": 0,
        "replacedWith": null,
        "display_name": "Medium-Term System Adequacy Outlook 2026-2030",
        "translations": null,
        "collection_id": null,
        "image": ""
      }
    },
    {
      "type": "Keyword",
      "data": {
        "keywordId": "440420",
        "name": "MTSAO",
        "url": "https://www.dailymaverick.co.za/article_tag//",
        "slug": "mtsao",
        "description": "",
        "articlesCount": 0,
        "replacedWith": null,
        "display_name": "MTSAO",
        "translations": null,
        "collection_id": null,
        "image": ""
      }
    }
  ],
  "short_summary": null,
  "source": null,
  "related": [],
  "options": [],
  "attachments": [
    {
      "id": "3082820",
      "name": "Op-ed-Yelland-Eskom-adequacy MAIN",
      "description": "(Photo: Unsplash / Andrey Metelev)",
      "focal": "50% 50%",
      "width": 0,
      "height": 0,
      "url": "https://cdn.dailymaverick.co.za/dailymaverick/wp-content/uploads/2023/08/andrey-metelev-qpAOxji4dAo-unsplash.jpg",
      "transforms": [
        {
          "x": "200",
          "y": "100",
          "url": "https://cdn.dailymaverick.co.za/i/uwhKf-H8UswUKqNUdU2MQ09VdQQ=/200x100/smart/filters:strip_exif()/file/dailymaverick/wp-content/uploads/2023/08/andrey-metelev-qpAOxji4dAo-unsplash.jpg"
        },
        {
          "x": "450",
          "y": "0",
          "url": "https://cdn.dailymaverick.co.za/i/nkM_F6wJbk7azN-E29ZV7iHv7bs=/450x0/smart/file/dailymaverick/wp-content/uploads/2023/08/andrey-metelev-qpAOxji4dAo-unsplash.jpg"
        },
        {
          "x": "800",
          "y": "0",
          "url": "https://cdn.dailymaverick.co.za/i/FNhOve5cOL0JQsYGecAFT3XisBA=/800x0/smart/filters:strip_exif()/file/dailymaverick/wp-content/uploads/2023/08/andrey-metelev-qpAOxji4dAo-unsplash.jpg"
        },
        {
          "x": "1200",
          "y": "0",
          "url": "https://cdn.dailymaverick.co.za/i/q4ibV8sTFkY7-k_ZoxfLsnbiVWw=/1200x0/smart/filters:strip_exif()/file/dailymaverick/wp-content/uploads/2023/08/andrey-metelev-qpAOxji4dAo-unsplash.jpg"
        },
        {
          "x": "1600",
          "y": "0",
          "url": "https://cdn.dailymaverick.co.za/i/FgxDfhuMIWxfvMCvPEzbcDi1C2Q=/1600x0/smart/filters:strip_exif()/file/dailymaverick/wp-content/uploads/2023/08/andrey-metelev-qpAOxji4dAo-unsplash.jpg"
        }
      ],
      "url_thumbnail": "https://cdn.dailymaverick.co.za/i/uwhKf-H8UswUKqNUdU2MQ09VdQQ=/200x100/smart/filters:strip_exif()/file/dailymaverick/wp-content/uploads/2023/08/andrey-metelev-qpAOxji4dAo-unsplash.jpg",
      "url_medium": "https://cdn.dailymaverick.co.za/i/nkM_F6wJbk7azN-E29ZV7iHv7bs=/450x0/smart/file/dailymaverick/wp-content/uploads/2023/08/andrey-metelev-qpAOxji4dAo-unsplash.jpg",
      "url_large": "https://cdn.dailymaverick.co.za/i/FNhOve5cOL0JQsYGecAFT3XisBA=/800x0/smart/filters:strip_exif()/file/dailymaverick/wp-content/uploads/2023/08/andrey-metelev-qpAOxji4dAo-unsplash.jpg",
      "url_xl": "https://cdn.dailymaverick.co.za/i/q4ibV8sTFkY7-k_ZoxfLsnbiVWw=/1200x0/smart/filters:strip_exif()/file/dailymaverick/wp-content/uploads/2023/08/andrey-metelev-qpAOxji4dAo-unsplash.jpg",
      "url_xxl": "https://cdn.dailymaverick.co.za/i/FgxDfhuMIWxfvMCvPEzbcDi1C2Q=/1600x0/smart/filters:strip_exif()/file/dailymaverick/wp-content/uploads/2023/08/andrey-metelev-qpAOxji4dAo-unsplash.jpg",
      "type": "image"
    }
  ],
  "inline_attachments": [
    {
      "id": "2959603",
      "name": " Created using Gemini",
      "description": "",
      "url": "https://cdn.dailymaverick.co.za/dailymaverick/wp-content/uploads/2025/11/Code_Generated_Image.png",
      "type": "inline_image"
    }
  ],
  "summary": "Eskom's latest report reveals that while South Africa's power supply might look good on paper, the reality is a precarious dance between regional shortages and grid congestion, with the looming retirement of coal plants threatening to plunge us back into the dark ages – unless, of course, our gas turbines arrive on time to save the day.",
  "introduction": "<ul><li>Eskom's MTSAO 2026-2030 Report assesses South Africa's power generation capacity and demand, highlighting regional inadequacies despite national supply sufficiency.</li><li>The report introduces a multinodal analysis, revealing potential local shortfalls and grid congestion that could lead to load shedding.</li><li>A looming supply cliff is anticipated as 9.5GW of capacity, including coal and hydro imports, is set to retire by 2030, raising risks of load shedding if new gas generation is delayed.</li><li>Transmission bottlenecks are increasingly critical, with key regions facing deficits, emphasizing the need for major upgrades to the grid infrastructure.</li></ul>",
  "template_type": null,
  "dm_custom_section_label": "Op-eds",
  "dm-key-theme": null,
  "dm-article-theme": null,
  "dm-user-need": null,
  "dm-disable-comments": false,
  "elements": [],
  "seo": {
    "search_title": "Risks flagged in Eskom’s 2026-30 system adequacy outlook require critical balancing act",
    "search_description": "The Eskom report portrays a power system entering a delicate transition. Adequacy risks now exist on both sides of the equation: shortfalls from delayed firm capacity and surpluses from rapid renewable growth. Managing this dual challenge demands careful synchronisation of generation, gas infrastructure and grid expansion.",
    "social_title": "Risks identified in Eskom’s 2026-30 system adequacy outlook require a critical balancing act",
    "social_description": "The Eskom report portrays a power system entering a delicate transition. Adequacy risks now exist on both sides of the equation: shortfalls from delayed firm capacity and surpluses from rapid renewable growth. Managing this dual challenge demands careful synchronisation of generation, gas infrastruc",
    "social_image": ""
  },
  "time_to_read": 295,
  "cached": true
}

Comments (0)

Scroll down to load comments...